Time and Work

Points to Remember


1 . If A can finish a piece of work in `n' days, then A's 1 day's work is 1/n .

2 . If the number of men engaged to do a piece of work is changed in the ratio a:b, the time required for the work will be changed in the ratio b:a.

3 . If A is X times as good a workman as B, then A will take 1/x of the time that B takes to do a certain work.

4 . If M1 persons can do `W1' works in D1 days for T1 hours and M2 persons can do `W2' works in D2 days for T2 hours then M1 D1 T1 W2 = M2 D2 T2W1.

If A can finish a work in `x' days and B can finish the same work in `y' days, then time taken by both to finish the work is xy/x+y days.

6 . If A and B together can do a piece of work in x days and A alone can do it in y days then B alone can do it in xy/y-z days.


Solved Examples


1 . 8 boys can arrange all the books of school library in 12 days. In how many days can 6 boys arrange them?
Ans: Ans: M1 D1 = M2 D2
D2= 8x12/6 = 16 days

2 . A can do a piece of work in 12 days and B alone can do it in 15 days. How much time will both take to finish the work?
Ans: A's 1 day's work = 1/12
B's 1 day's work = 1/15
(A+B)'s 1 day's work = 1/12 + 1/15 =3/20
Therefore both together can finish the work in
time and work

3. A and B together can do a piece of work in 12 days. B alone can finish it in 30 days. In how many days can A alone finish the work?
Ans:(A+B)'s 1 day's work = 1/12
B's 1 day's work = 1/30
A's 1 day's work = 1/12 - 1/30 = 1/20
Therefore A alone can finish the work in 20 days.
time and work formula

4 . 16 men can do a piece of work in 10 days. How many men are needed to complete the work in 40 days?
Ans:M1 D1 = M2 D2
M1 = 16, D1 = 10, D2 = 40
16x10 = M2 x 40
M2 = 16 x 10/40 = 4 men.

time and work formula

ANSWERS TO PRACTICE TEST

1 . (1)  2 . (3)

You can reach us at:

aimgovtjob@gmail.com

Popular Posts
Banking Interview questions

IBPS Interview Questions With Answers
IBPS Interview Questions With Answers for Clerk, Probationary Officers (PO) and Specialist Officers (SO).

Banking Points

Important Points in Indian Banking
Must remember banking important points for all competitive exams.

Bank Head Quarters

Banks and their Headquarters
All nationalized and public sector banks headquarters.

Bank Tag Lines

Banks and their Tag Lines
All nationalized banks with their tag lines.

Alphabet Analogy

Computer Awareness
Classification of Computers based on their size and ability.


POPULAR TAGS
Analogy Blood Relations Computer Basics Basics of Internet Seating Arrangement Odd Man Out Direction Sense Computer Shortcuts


Groups Exam Materials
TSPSC Logo

Group II Materials
Group II preperation plan

telangana charitra

Telangana Charitra
Telangana Charitra for TSPSC Group II Exams.

More from us